Respuesta :
Contractor 1: y = 200 + 50x
Contractor 2: y = 150 + 55x
50 and 55 are the variable costs incurred in doing the project. These costs will only be implemented when x changes. X is the variable that may represent the number of hours worked, number of people added to complete the task.
200 and 150 are the fixed cost of the project. Mrs. Solar must pay the cost regardless of the changes happening in x.
For example: Both contractors need to add 15 additional people to complete the task. Then:
Contractor 1 : y = 200 + 50(15) = 200 + 750 = 950
Contractor 2 : y = 150 + 55(15) = 150 + 825 = 975 è Contractor 1 is the best option:
If x = 10 additional people
Contractor 1: y = 200 + 50(10) = 200 + 500 = 700
Contractor 2: y = 150 + 55(10) = 150 + 550 = 700 è Any contractor is the best option
If x = 5 additional people
Contractor 1: y = 200 + 50(5) = 200 + 250 = 450
Contractor 2: y = 150 + 55(5) = 150 + 275 = 425 è Contractor 2 is the best option
Contractor 2: y = 150 + 55x
50 and 55 are the variable costs incurred in doing the project. These costs will only be implemented when x changes. X is the variable that may represent the number of hours worked, number of people added to complete the task.
200 and 150 are the fixed cost of the project. Mrs. Solar must pay the cost regardless of the changes happening in x.
For example: Both contractors need to add 15 additional people to complete the task. Then:
Contractor 1 : y = 200 + 50(15) = 200 + 750 = 950
Contractor 2 : y = 150 + 55(15) = 150 + 825 = 975 è Contractor 1 is the best option:
If x = 10 additional people
Contractor 1: y = 200 + 50(10) = 200 + 500 = 700
Contractor 2: y = 150 + 55(10) = 150 + 550 = 700 è Any contractor is the best option
If x = 5 additional people
Contractor 1: y = 200 + 50(5) = 200 + 250 = 450
Contractor 2: y = 150 + 55(5) = 150 + 275 = 425 è Contractor 2 is the best option