If 6 men did a piece of work in 3 days, how many men will be needed to do the same piece of work in 2 days? A. 9 men B. 8 men C. 7 men D. 6 men

The number of men which it will take which will be needed for the same job to be completed in 2 days is; Choice A; 9 men.
It follows from the task content that 6 men did the work in 3 days and hence, to determine the number of men capable of completing the work 2 days, we must evaluate as follows;
Total work = 6men × 3 days = 18 men days.
Hence, for 2 days; = 18/2 = 9 men.