The preparation of a direct labor budget for Gundy Company for the 6-months ending June 30, 2022, is as follows:
Gundy Company
Quarterly Direct Labor Budget
For the 6 months ending June 30, 2022:
Quarter 1 Quarter 2
Production units 5,000 7,000
Labor-hour per unit 1.6 1.6
Total direct labor-hours 8,000 11,200
Hourly wage rate $15 $15
Total direct labor costs $120,000 $168,000
What is a direct labor budget?
The direct labor budget is a budget that calculates the total labor hours required to produce the budgeted units, according to the production budget.
The total direct labor hours are used to multiply the wage rate per hour to obtain the total budgeted direct labor costs.
Data and Calculations:
Quarter 1 Quarter 2
Production units 5,000 7,000
Labor-hour per unit 1.6 1.6
Total direct labor-hours 8,000 11,200
Hourly wage rate $15 $15
Total direct labor costs $120,000 $168,000