A construction company plans to invest in a building project. There is a 25% chance that the company will lose $40,000, a 35% chance of a break even, and a 40% chance of a $30,000 profit. Based on this information, what should the company do?

SHOW YOUR WORK!!

A) The expected value is $2,000, so the company should proceed with the project.

B) The expected value is $22,000, so the company should proceed with the project.

C) The expected value is - $2,000, so the company should not proceed with the project.

D) The expected value is $-22,000, so the company should not proceed with the project.

Respuesta :

Hagrid
Thank you for posting your question here at brainly. I hope the answer will help you. Feel free to ask more questions.

C) The expected value is - $2,000, so the company should not proceed with the project.