in order to produce a new product, a firm must lease equipment at a cost of $50,000 per year. the managers feel that they can sell 10,000 units per year at a price of $35. what is the highest variable cost that will allow the firm to at least break even on this project?

Respuesta :

Answer:350000

Explanation:

if you do simple math and do the problem 10000 X 35=350000 that is the end of the question since it is asking you to find the HIGHEST variable cost