From a 200-ton pile of coal, a conveyor belt removes
1
ton per minute. By lunchtime, only of a ton was left
on the pile. Which equation can be used to find x, the
number of minutes the conveyor belt was used to remove
coal before lunch?

Respuesta :

Answer:

56 min

Step-by-step explanation: