Answer:
NPV = $100.4002 rounded off to $100.40
Explanation:
The NPV or net present value is the present value of a project or business's cash flows which are calculated by deducting the cash outflows from the cash inflows. NPV is a tool or criteria used for investment and project appraisal. The NPV can be calculated as follows,
NPV = CF1 / (1+r) + CF2 / (1+r)^2 + .... + CFn / (1+r)^n - Initial Outlay
Where,
NPV = 660 / (1+0.075) + [ -85 / (1+0.075)^2] - 440
NPV = $100.4002 rounded off to $100.40