Answer:
$500
Explanation:
Calculation to determine the amount of batch-level costs that will be allocated to the product
Using this formula
Allocation rate=(Total batch level overhead cost/Total activity base ) * Set-ups
Let plug in the formula
Allocation rate=( $10,000/400 set-ups) *20 set-ups
Allocation rate=$25 per set-up *20 set-ups
Allocation rate=$500
Therefore the amount of batch-level costs that will be allocated to the product is $500