Answer:
JDI should buy the part
Explanation:
The decision tree is shown in the file attached below.
From the information given:
Provided that the expected values denote the costs; JDI is expected to select the lowest expected value and make the part.
JDI expected monetary cost = $140000
Its buy decision = $150000