Show work. Will mark branliest​

Answer:10
Step-by-step explanation:
12 x 30 to see how many bottles per hour
360 x 8 to see how many it makes in a day
Divide 28,000 by 2,800 to see how many days it would take.
Step-by-step explanation:
first u will find how much bottles in 8 hours so that will be 60/2minutes =30so 30*12ottles=to 360 bottles per hour so 8*360=2,880 so u will do 28,000/2,880 it will be. 10 days of work.