Respuesta :

Baraq

Answer:

1. Split Stories to eliminate dependencies;

2. Move Stories on their team's backlog to another team;

Explanation:

There are two established strategies a Product Owner can use during Program Increment Planning to minimize dependencies. These includes

1. Split Stories to eliminate dependencies; this help to define the different story for the Team backlog and thereby making others understand it in simple terms.

2. Move Stories on their team's backlog to another team;