The critical path for a project was found to be 37 days. The variances total 27. What is probability of completing in 43 days? Below is information that might be useful to answer the question. Answer to 2 decimal points

Respuesta :

Answer:

0.1241.

Step-by-step explanation:

So, from the question we are given the following parameters or information or data which are going to help us in solving this particular question/problem. They are; [1]. The critical path for a project = 37 days, the variances total or variance of critical path or sum of variance on critical path]². = 27, the desired completion time/day = 43 days.

So, we will be making use of the formula given below;

The number of standard deviation = desired completion time/day - critical time or sum of critical path times ÷√[variance of critical path or sum of variance on critical path]².

The number of standard deviation = 43 - 37 ÷ √27 = 1.1547.

Thus, the probability of completing in 43 days = P(Z > 1.1547) = 0.1241.