Below is a set of projects aimed at cleaning up a city's recreational areas.
Determine whether the city should undertake the cleanup effort. Assume the city has enough money in its budget to undertake all projects.

Project Marginal Cost Marginal Benefit Clean Up? (Y/N)
North Park $13,000 $16,000
Upper River Beach 6,000 8,000
South Shore 29,000 30,000
Green Creek 900 1,300

Respuesta :

Answer:

North Park $13,000 $16,000 N

Upper River Beach 6,000 8,000  Y

South Shore 29,000 30,000  Y

Green Creek 900 1,300 N

Explanation:

The cleanup will happen in the area where the marginal benefit is more than the marginal cost. the North park will not be cleaned up. River beach will be cleaned Up. South shore will be cleaned up. Green creak will not be cleaned up.