duhgdgFog2006 duhgdgFog2006 18-03-2020 Business contestada Complete the following MRP record and provide the planned order releases for Week 1. Lead time is 2 weeks. Safety stock is 3. Use LFL lot sizes. Part X Week 1 2 3 4 Gross Requirements 32 16 34 40 Scheduled Receipts 10 Projected On-Hand inventory 46 Planned Order Releases a. 29 b. 26 c. 14 d. 34