Coronado Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are estimated to total $292,552 for the year, and machine usage is estimated at 126,100 hours. For the year, $413,432 of overhead costs are incurred and 130,100 hours are used. (a) Compute the manufacturing overhead rate for the year. (Round answer to 2 decimal places, e.g. 1.25.) Manufacturing overhead rate $Type your answer here per machine hour

Respuesta :

Answer:

Estimated manufacturing overhead rate= $2.32 per machine hour.

Explanation:

Giving the following information:

Overhead costs are estimated to total $292,552 for the year, and machine usage is estimated at 126,100 hours.

To calculate the estimated manufacturing overhead rate we need to use the following formula:

Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

Estimated manufacturing overhead rate= 292,552/126,100= $2.32 per machine hour.