Answer:
A) number of projects completed
Explanation:
As Gulshan Parvana is operating a machine shop which generate revenue based on the bids on small projects. So, the most suitable basis for the allocation of utility cost is number of projects completed in the month. This basis drives the utility cost. As revenue and cost are based on the number of bids on projects won and completed in the period is the most suitable basis for cost assignment.