Answer:
i) see below
ii) end of week 41; 90,000 penalty
iii) no change required
Explanation:
i) There appear to be two separate "no predecessor" tasks: A and G. There appear to be two separate "no successor" tasks: I and Q. A representation of the network is shown below. The pink bar across the middle is the critical path.
The pink task K is shown as fixed, dependent upon the hotel booking (see part iii).
Where starts or ends line up, a dependency is implied. Where there is some ambiguity in that regard, the specific dependency is shown with a letter.
In general, tasks are shown with the latest possible start. (K is an exception.) Slack time is shown with a dash.
__
ii) The critical path has a length of 41 weeks. That is 3 weeks longer than the required duration, so a penalty of 3×30,000 = 90,000 is expected.
__
iii) Activity K can start as early as week 10 or as late as week 25. There is no need to change the hotel booking for weeks 12 and 13.