Answer:
$83
Explanation:
The formula to compute the rate charged per hour of labor is shown below:
= Total budgeted costs of Time charges ÷ budgeted hours + profit margin per hour of labor
= $318,200 ÷ 7,400 hours + $40
= $43 + $40
= $83
We simply compute the per hour and then add the profit margin per hour so that the correct rate per hour can come
All other information which is given is not relevant. Hence, ignored it