Answer:
Completing the operation will require 9.765625 hours.
Explanation:
First, let's check which of the stages will be the process limitation:
Regarding the pump, it can perform up to 120 cy/h. The trucks will deliver 8 cy every 15 min, i.e., 32 cy/h, then this is the smaller capacity within the whole process.
Now, let's establish a simple relation:
Placement speed x Efficiency = Placed quantity / time,
solving for time. we have
[tex]t = \frac{q}{\epsilon s} = \frac{250 cy}{0.8\times 32\frac{cy}{h}} = \mathbf{9.765625 h}.[/tex]