You are analyzing the project performance at the end of Week 5. Activity "B" is 40% complete and its actual cost is 15. What is the Schedule Performance Index of this activity? Use two decimal places.
A) 0.40
B) 0.75
C) 1.25
D) 1.00

Respuesta :